Admiral Way North and South Bridges Seismic Project Updates

Stay up to date with our Bridge Seismic Retrofit Work



Seattle Department of Transportation logo



Admiral Way North and South Bridges Seismic Project Updates

Construction updates: October 3, 2024 

Construction on retrofits to help the Admiral Way North and South Bridges better withstand earthquakes is ongoing! Crews are preparing to pour concrete to retrofit the bridge’s infill walls and floor beams by installing reinforcing bars and other reinforcing components. They are continuing to work on the bridge’s expansion joints and piers and will be installing a new light pole in the coming weeks.  

On *Friday, October 4th, we will be transitioning into our next phase of sidewalk and lane closures*. The south bridge will be closed to people driving, walking, biking, and rolling, with traffic shifted onto the north bridge. One eastbound lane and one westbound lane will be maintained for car travel. People walking, biking, and rolling will be able to travel across the bridge using the sidewalk on the south bridge. 

As a reminder, *the segment of Fairmount Ave SW beneath the bridge is closed to people walking, biking, rolling, and driving for the duration of construction (10 months) *to ensure their safety and allow our crews to work as efficiently as possible. We anticipate that construction will last approximately 10 months. Construction schedules are subject to change and depend on factors such as weather and availability of crews and materials. 

We will continue to provide updates on construction activities on our project webpage [ https://www.seattle.gov/transportation/projects-and-programs/programs/bridges-stairs-and-other-structures/bridges/sw-admiral-way-bridge-retrofit?utm_medium=email&utm_source=govdelivery ] and via these email updates. Please feel free to share this email with your neighbors and encourage them to sign up for our email updates [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/new?qsp=WASEATTLE_8 ] to stay informed on the project.    

 *What to expect during construction*    

We understand our closure of Fairmount Ave N for the duration of construction and ongoing lane closures impact everyone who uses the bridge and Fairmount Ave N. We are actively working to ensure our traffic control plan runs smoothly and impacts community members traveling as little as possible.  

In addition to the full closure of Fairmount Ave N below the bridge and ongoing lane closures you can expect:       


* Work in the public right-of-way near your home or business    

* Temporary on-street parking restrictions, with "no park" signs placed 72 hours in advance   

* Staged construction equipment and materials as well as noise, dust, and vibrations in the work area  

* Typical weekday work hours of 7 AM – 5 PM, Monday through Friday

________________________________________________________________________



*Thank you! *     

Thank you for your interest in the Admiral Way North and South Bridge Seismic project and for your patience during construction.    

 Sincerely,       

Matthew Howard  

Communications and Outreach Lead      

Admiral Way North and South Bridge Seismic Project   

"You are receiving this email because you have expressed interest in receiving updates on the Admiral Way North and South Bridge Seismic project." 






*Seattle Department of Transportation*

700 5th Avenue

Suite 3800

Seattle, WA 98104

*Phone: 206-684-7623*

facebook [ https://www.facebook.com/SeattleDOT/?utm_medium=email&utm_source=govdelivery ]front porch [ https://sdotblog.seattle.gov/?utm_medium=email&utm_source=govdelivery ]r s s feed [ https://sdotblog.seattle.gov/feed/?utm_medium=email&utm_source=govdelivery ]twitter [ https://twitter.com/seattledot?utm_medium=email&utm_source=govdelivery ]flickr [ https://www.flickr.com/photos/sdot_photos?utm_medium=email&utm_source=govdelivery ]instagram [ https://www.instagram.com/seattledot/?utm_medium=email&utm_source=govdelivery ]youtube [ https://www.youtube.com/seattledot?utm_medium=email&utm_source=govdelivery ]linkedin [ https://www.linkedin.com/company/seattle-department-of-transportation?utm_medium=email&utm_source=govdelivery ] seattle dot gov

Manage Preferences [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/edit?preferences=true#tab1 ]  |  Unsubscribe [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/one_click_unsubscribe?verification=5.7e4abd93610d77ba0dce3e5196581a5c&destination=mshinji3056%40gmail.com ]  |  Contact Us [ https://www.seattle.gov/transportation/about-sdot/contact-us?utm_medium=email&utm_source=govdelivery ]  |  Help [ https://subscriberhelp.govdelivery.com/ ] |  Privacy [ https://www.seattle.gov/privacy-statement?utm_medium=email&utm_source=govdelivery ]




________________________________________________________________________

This email was sent to mshinji3056@gmail.com using GovDelivery Communications Cloud on behalf of: City of Seattle, Washington · 707 17th St, Suite 4000 · Denver, CO 80202 GovDelivery logo [ https://subscriberhelp.granicus.com/?utm_medium=email&utm_source=govdelivery ]

body .abe-column-block { min-height: 5px; } table.gd_combo_table img {margin-left:10px; margin-right:10px;} table.gd_combo_table div.govd_image_display img, table.gd_combo_table td.gd_combo_image_cell img {margin-left:0px; margin-right:0px;} table.govd_hr {min-width: 100%;}
  • [登録者]City of Seattle
  • [言語]日本語
  • [エリア]Seattle, WA
  • 登録日 : 2024/10/03
  • 掲載日 : 2024/10/03
  • 変更日 : 2024/10/03
  • 総閲覧数 : 39 人
Web Access No.2212323