Beacon Ave S & 15th Ave S Safety Project Update - January 31

Construction updates for February 1 - 14



Seattle Department of Transportation logo



Beacon Ave S & 15th Ave S Safety Project Update

________________________________________________________________________



*Construction of the Beacon Ave S and 15th Ave S Safety Project is underway!* Crews will work in segments along the project area through spring 2025.

Continue visiting our project website [ https://www.seattle.gov/transportation/projects-and-programs/programs/bike-program/protected-bike-lanes/beacon-hill-bike-route?utm_medium=email&utm_source=govdelivery ] or subscribe to our email list [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/topics?qsp=WASEATTLE_8 ] for bi-weekly updates on construction activities. 

________________________________________________________________________



Construction update

Our crews recently completed the majority of our work on 15th Ave S including installing protected bike lanes and repairing sections of sidewalk from S Charles St to S Bayview St. 15th Ave S is now reopened to traffic in both directions, but* the bike lanes remain closed until we complete drainage work and clear the lanes of debris*. Crews will return to 15th Ave S this spring to complete roadway striping, plantings, and final drainage work.

Over the next few weeks, you'll see our crews doing the following work throughout the project area:


* Removing roadway pavement and sidewalk and installing storm drain improvements on the east side and center lane of Beacon Ave S near the intersection of S Lander St
* Removing roadway pavement and sidewalk and installing storm drain improvements on the east side of Beacon Ave S near the intersection of S Hanford St
* Continuing electrical improvements and then restoring roadway, sidewalks, and curb ramps on the west side of Beacon Ave S near the intersection of S Hanford St
* Removing 3 trees near the intersection of Beacon Ave S and S Lander St outside of the Hilltop Red Apple as early as February 1. We will plant 9 new trees in the area to replace these trees this spring.
* Evaluating trees on Beacon Ave S south of S McClellan St. We will work with an arborist to evaluate all options for retaining these trees before considering removal. We hope none of these trees will need to be removed, but sometimes removal is the only option to construct ADA-compliant sidewalks. For any tree that must be removed, we will replant 3 more nearby that are sidewalk-friendly and better suited for the environment.

*Please note that some of this work is weather dependent and subject to schedule changes. 

Traffic control and what to expect in the project area over the next couple of weeks

Traffic control to expect during construction work over the next few weeks

________________________________________________________________________



________________________________________________________________________



Tree Removal Update

January 31 update: Thank you to each person who reached out to us this week advocating for the trees along Beacon Ave S south of S McClellan St under evaluation. We understand that it can be alarming to see so many trees posted for evaluation, but we assure you that we are working with an arborist to explore every other option before we consider removals. It is possible that these evaluations will result in no tree removals.

These tree evaluations will be taking place over the next few weeks. After the evaluations, we will offer a public site walk with our arborist to explain the results to those in attendance. Please subscribe to our email list or keep an eye out for updates on our project webpage to hear about when this public site walk will take place. 

 

January 10 update: We are beginning to inspect tree roots along the project corridor on Beacon Ave S south of S Lander St to evaluate the tree root systems and health to determine need for removal to make sidewalks ADA-compliant. If any trees need to be removed, our arborist will post the trees for 2 weeks before our crews remove them and repair nearby sidewalks and curb ramps.

 

We may need to remove more trees than the three we initially identified during design phase. As we began sidewalk repair work on the project corridor, we're finding that more trees have root systems that are too shallow and overgrown under the sidewalk. If we exhaust all other design options to build ADA-compliant sidewalks, we will need to post and remove trees. We are trying our best to retain as many trees as possible. We will continue to inspect tree roots as we move southward with our sidewalk repair work and will share additional information about tree removals as they become available.

________________________________________________________________________



*Business owners and managers*

Please fill out this construction survey [ https://survey.alchemer.com/s3/7863357/6592169a0975?utm_medium=email&utm_source=govdelivery ] so we can keep you informed and minimize impacts to your business during construction. You may also request a paper copy by leaving us a voicemail at (206) 900-8728 [ tel:%20+1%20(206)%20900-8728 ] or emailing us at Beacon15thSafety@seattle.gov.

The survey is available in English, [ https://survey.alchemer.com/s3/7863357/6592169a0975?utm_medium=email&utm_source=govdelivery ]Spanish,  [ https://survey.alchemer.com/s3/7863357/3ff0336f0841?utm_medium=email&utm_source=govdelivery ]Amharic, [ https://survey.alchemer.com/s3/7863357/ac1329f48bc3?utm_medium=email&utm_source=govdelivery ]Simplified Chinese,  [ https://survey.alchemer.com/s3/7863357/11bd0e37baf6?utm_medium=email&utm_source=govdelivery ]Traditional Chinese,  [ https://survey.alchemer.com/s3/7863357/cfbd6fe8e97f?utm_medium=email&utm_source=govdelivery ]Tagalog,  [ https://survey.alchemer.com/s3/7863357/5571bc5da205?utm_medium=email&utm_source=govdelivery ]Vietnamese,  [ https://survey.alchemer.com/s3/7863357/e4e2685140d2?utm_medium=email&utm_source=govdelivery ]Somali, [ https://survey.alchemer.com/s3/7863357/eb9a76299b2c?utm_medium=email&utm_source=govdelivery ]and Tigrinya. [ https://survey.alchemer.com/s3/7863357/1dfc6c9a0261?utm_medium=email&utm_source=govdelivery ]

Thank you to all the business owners and managers who have already filled out our survey online or in-person during our door-to-door outreach in late June and early July!

________________________________________________________________________



*What to Expect During Construction*

Typical work hours are Monday – Friday, from 7:00 AM to 5:00 PM. During this time you can expect: 


* Temporary traffic revisions to accommodate construction vehicles
* Temporary parking restrictions near work zone
* Noisy construction activities, such as backup alarms for safety, heavy vehicle use, and the use of power tools.
* Please note that much of this work is weather dependent and subject to schedule changes. 

________________________________________________________________________



Changes coming to Beacon Ave S and 15th Ave S

* *Repaired sections of sidewalk* near every intersection along the entire route
* *New APS pedestrian push buttons* at every crossing at S Hanford St and Beacon Ave S and at the south and west crossings of 15th Ave S and S College St
* *62 new or rebuilt curb ramps*. When this project is complete, people who use wheels will be able to safely travel from Dr. Jose Rizal Bridge to S Spokane St.
* *Concrete-protected bike lanes* on both sides of 15th Ave S
* *Post-protected bike lanes* on both sides of Beacon Ave S
* *New bike signals* at the intersections of S Charles St & Golf Dr S, 15th Ave S & S College St, and 15th Ave S & Beacon Ave S
* *New bus stop islands* on both sides of Beacon Ave S at S Hanford St and outside of Beacon Hill Station
Map illustrating changes coming to Beacon Ave S and 15th Ave S

Changes coming to Beacon Ave S and 15th Ave S as part of this Safety Project

Learn more about how we're improving safety in North Beacon Hill [ https://www.seattle.gov/transportation/projects-and-programs/programs/bike-program/protected-bike-lanes/beacon-hill-bike-route?utm_medium=email&utm_source=govdelivery ]

________________________________________________________________________



How to stay informed

* Call our project hotline at (206) 900-8728 [ tel:%20+1%20(206)%20900-8728 ]
* Email us at Beacon15thSafety@seattle.gov.
* Visit our project webpage [ https://www.seattle.gov/transportation/projects-and-programs/programs/bike-program/protected-bike-lanes/beacon-hill-bike-route?utm_medium=email&utm_source=govdelivery ] to:
* Read about project progress
* Sign up for email updates

Thank you,

Ching Chan

Public Engagement Lead

Levy to Move Seattle Logo
________________________________________________________________________



For translation services, please call (206) 900-8728 [ tel:%20+1%20(206)%20900-8728 ] and leave a message clearly stating the language you prefer.

________________________________________________________________________



Blue Bullhorn Icon
 
Sign up for the SDOT Newsletter

"Stay up to date on Seattle's transportation news. You'll receive our top highlights delivered straight to your inbox each month. – ""Subscribe here" [ https://links-1.govdelivery.com/CL0/https:%2F%2Fpublic.govdelivery.com%2Faccounts%2FWASEATTLE%2Fsubscriber%2Fnew%3Ftopic_id=WASEATTLE_353/1/0100019230e79298-055f5089-b93c-47aa-a827-b292f38c3bfa-000000/QdPe2xxfScc_oOXY7XV7dmtfjxyoDDb0uUhDZMvDh8I=372 ]". " [ https://sdotblog.seattle.gov/2024/09/24/mayor-harrells-2025-2026-proposed-budget-for-sdot/?utm_medium=email&utm_source=govdelivery ]








*Seattle Department of Transportation*

700 5th Avenue

Suite 3800

Seattle, WA 98104

*Phone: 206-684-7623*

facebook [ https://www.facebook.com/SeattleDOT/?utm_medium=email&utm_source=govdelivery ]front porch [ https://sdotblog.seattle.gov/?utm_medium=email&utm_source=govdelivery ]r s s feed [ https://sdotblog.seattle.gov/feed/?utm_medium=email&utm_source=govdelivery ]twitter [ https://twitter.com/seattledot?utm_medium=email&utm_source=govdelivery ]flickr [ https://www.flickr.com/photos/sdot_photos?utm_medium=email&utm_source=govdelivery ]instagram [ https://www.instagram.com/seattledot/?utm_medium=email&utm_source=govdelivery ]youtube [ https://www.youtube.com/seattledot?utm_medium=email&utm_source=govdelivery ]linkedin [ https://www.linkedin.com/company/seattle-department-of-transportation?utm_medium=email&utm_source=govdelivery ] seattle dot gov

Manage Preferences [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/edit?preferences=true#tab1 ]  |  Unsubscribe [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/one_click_unsubscribe?verification=5.7e4abd93610d77ba0dce3e5196581a5c&destination=mshinji3056%40gmail.com ]  |  Contact Us [ https://www.seattle.gov/transportation/about-sdot/contact-us?utm_medium=email&utm_source=govdelivery ]  |  Help [ https://subscriberhelp.govdelivery.com/ ] |  Privacy [ https://www.seattle.gov/privacy-statement?utm_medium=email&utm_source=govdelivery ]




________________________________________________________________________

This email was sent to mshinji3056@gmail.com using GovDelivery Communications Cloud on behalf of: City of Seattle, Washington · 707 17th St, Suite 4000 · Denver, CO 80202 GovDelivery logo [ https://subscriberhelp.granicus.com/?utm_medium=email&utm_source=govdelivery ]

body .abe-column-block { min-height: 5px; } table.gd_combo_table img {margin-left:10px; margin-right:10px;} table.gd_combo_table div.govd_image_display img, table.gd_combo_table td.gd_combo_image_cell img {margin-left:0px; margin-right:0px;} table.govd_hr {min-width: 100%;}
  • [登録者]City of Seattle
  • [言語]日本語
  • [エリア]Seattle, WA
  • 登録日 : 2025/01/31
  • 掲載日 : 2025/01/31
  • 変更日 : 2025/01/31
  • 総閲覧数 : 28 人
Web Access No.2508227