Beacon Ave S & 15th Ave S Safety Project Update - November 8

Construction updates for November 11 - 22



Seattle Department of Transportation logo



Beacon Ave S & 15th Ave S Safety Project Update

________________________________________________________________________



*Construction of the Beacon Ave S and 15th Ave S Safety Project is underway!* Crews will work in segments along the project area through spring 2025.

Continue visiting our project website [ https://www.seattle.gov/transportation/projects-and-programs/programs/bike-program/protected-bike-lanes/beacon-hill-bike-route?utm_medium=email&utm_source=govdelivery ] or subscribe to our email list [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/topics?qsp=WASEATTLE_8 ] for bi-weekly updates on construction activities. 

________________________________________________________________________



Construction update

Over the next couple of weeks, you'll see our crews doing the following work throughout the project area:

*15th Ave S from S Judkins St to S State St*


* Crews will continue installing concrete buffer for protected bike lanes on the *east and west sides* of 15th Ave S from S Judkins St to S State St. This work will *permanently remove parking* on the east side of 15th Ave S from S Judkins St to S State St.

*15th Ave S from S Plum St to S College St*


* Pour new sidewalk and curb ramps on the west side of 15th Ave S near S Plum St and on the east side of 15th Ave S near S College St
* Remove roadway pavement and sidewalk and install storm drain and electrical improvements on the west side of 15th Ave S near S College St

*15th Ave S and Beacon Ave S*


* Remove sidewalk and road pavement and begin underground electrical work at the northeast corner of the 15th Ave S and Beacon Ave S intersection and at the 15th Ave S and S Bayview St intersection.

*Please note that some of this work is weather dependent and subject to schedule changes.

Traffic control planned in the project area
________________________________________________________________________



*Construction progress*
Crews removing sidewalk on 15th Ave S near S Plum and S Hill St before replacement

Crews removing existing sidewalk on 15th Ave S near S Judkins St

Crews installing storm drain improvements on 15th Ave S near S Plum St

Crews installing storm drain improvements on 15th Ave S near S Plum St

________________________________________________________________________



*Business owners and managers*

Please fill out this construction survey [ https://survey.alchemer.com/s3/7863357/6592169a0975?utm_medium=email&utm_source=govdelivery ] so we can keep you informed and minimize impacts to your business during construction. You may also request a paper copy by leaving us a voicemail at (206) 900-8728 [ tel:%20+1%20(206)%20900-8728 ] or emailing us at Beacon15thSafety@seattle.gov.

The survey is available in English, [ https://survey.alchemer.com/s3/7863357/6592169a0975?utm_medium=email&utm_source=govdelivery ]Spanish,  [ https://survey.alchemer.com/s3/7863357/3ff0336f0841?utm_medium=email&utm_source=govdelivery ]Amharic, [ https://survey.alchemer.com/s3/7863357/ac1329f48bc3?utm_medium=email&utm_source=govdelivery ]Simplified Chinese,  [ https://survey.alchemer.com/s3/7863357/11bd0e37baf6?utm_medium=email&utm_source=govdelivery ]Traditional Chinese,  [ https://survey.alchemer.com/s3/7863357/cfbd6fe8e97f?utm_medium=email&utm_source=govdelivery ]Tagalog,  [ https://survey.alchemer.com/s3/7863357/5571bc5da205?utm_medium=email&utm_source=govdelivery ]Vietnamese,  [ https://survey.alchemer.com/s3/7863357/e4e2685140d2?utm_medium=email&utm_source=govdelivery ]Somali, [ https://survey.alchemer.com/s3/7863357/eb9a76299b2c?utm_medium=email&utm_source=govdelivery ]and Tigrinya. [ https://survey.alchemer.com/s3/7863357/1dfc6c9a0261?utm_medium=email&utm_source=govdelivery ]

Thank you to all the business owners and managers who have already filled out our survey online or in-person during our door-to-door outreach in late June and early July!

________________________________________________________________________



*What to Expect During Construction*

Typical work hours are Monday – Friday, from 7:00 AM to 5:00 PM. During this time you can expect: 


* Temporary traffic revisions to accommodate construction vehicles
* Temporary parking restrictions near work zone
* Noisy construction activities, such as backup alarms for safety, heavy vehicle use, and the use of power tools.
* Please note that much of this work is weather dependent and subject to schedule changes. 

________________________________________________________________________



Changes coming to Beacon Ave S and 15th Ave S

* *Repaired sections of sidewalk* near every intersection along the entire route
* *New APS pedestrian push buttons* at every crossing at S Hanford St and Beacon Ave S and at the south and west crossings of 15th Ave S and S College St
* *62 new or rebuilt curb ramps*. When this project is complete, people who use wheels will be able to safely travel from Dr. Jose Rizal Bridge to S Spokane St.
* *Concrete-protected bike lanes* on both sides of 15th Ave S
* *Post-protected bike lanes* on both sides of Beacon Ave S
* *New bike signals* at the intersections of S Charles St & Golf Dr S, 15th Ave S & S College St, and 15th Ave S & Beacon Ave S
* *New bus stop islands* on both sides of Beacon Ave S at S Hanford St and outside of Beacon Hill Station
Map illustrating changes coming to Beacon Ave S and 15th Ave S

Changes coming to Beacon Ave S and 15th Ave S as part of this Safety Project

Learn more about how we're improving safety in North Beacon Hill [ https://www.seattle.gov/transportation/projects-and-programs/programs/bike-program/protected-bike-lanes/beacon-hill-bike-route?utm_medium=email&utm_source=govdelivery ]

________________________________________________________________________



How to stay informed

* Call our project hotline at (206) 900-8728 [ tel:%20+1%20(206)%20900-8728 ]
* Email us at Beacon15thSafety@seattle.gov.
* Visit our project webpage [ https://www.seattle.gov/transportation/projects-and-programs/programs/bike-program/protected-bike-lanes/beacon-hill-bike-route?utm_medium=email&utm_source=govdelivery ] to:
* Read about project progress
* Sign up for email updates

Thank you,

Ching Chan

Public Engagement Lead

Levy to Move Seattle Logo
________________________________________________________________________



For translation services, please call (206) 900-8728 [ tel:%20+1%20(206)%20900-8728 ] and leave a message clearly stating the language you prefer.

________________________________________________________________________



Blue Bullhorn Icon
 
Sign up for the SDOT Newsletter

"Stay up to date on Seattle's transportation news. You'll receive our top highlights delivered straight to your inbox each month. – ""Subscribe here" [ https://links-1.govdelivery.com/CL0/https:%2F%2Fpublic.govdelivery.com%2Faccounts%2FWASEATTLE%2Fsubscriber%2Fnew%3Ftopic_id=WASEATTLE_353/1/0100019230e79298-055f5089-b93c-47aa-a827-b292f38c3bfa-000000/QdPe2xxfScc_oOXY7XV7dmtfjxyoDDb0uUhDZMvDh8I=372 ]". " [ https://sdotblog.seattle.gov/2024/09/24/mayor-harrells-2025-2026-proposed-budget-for-sdot/?utm_medium=email&utm_source=govdelivery ]








*Seattle Department of Transportation*

700 5th Avenue

Suite 3800

Seattle, WA 98104

*Phone: 206-684-7623*

facebook [ https://www.facebook.com/SeattleDOT/?utm_medium=email&utm_source=govdelivery ]front porch [ https://sdotblog.seattle.gov/?utm_medium=email&utm_source=govdelivery ]r s s feed [ https://sdotblog.seattle.gov/feed/?utm_medium=email&utm_source=govdelivery ]twitter [ https://twitter.com/seattledot?utm_medium=email&utm_source=govdelivery ]flickr [ https://www.flickr.com/photos/sdot_photos?utm_medium=email&utm_source=govdelivery ]instagram [ https://www.instagram.com/seattledot/?utm_medium=email&utm_source=govdelivery ]youtube [ https://www.youtube.com/seattledot?utm_medium=email&utm_source=govdelivery ]linkedin [ https://www.linkedin.com/company/seattle-department-of-transportation?utm_medium=email&utm_source=govdelivery ] seattle dot gov

Manage Preferences [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/edit?preferences=true#tab1 ]  |  Unsubscribe [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/one_click_unsubscribe?verification=5.7e4abd93610d77ba0dce3e5196581a5c&destination=mshinji3056%40gmail.com ]  |  Contact Us [ https://www.seattle.gov/transportation/about-sdot/contact-us?utm_medium=email&utm_source=govdelivery ]  |  Help [ https://subscriberhelp.govdelivery.com/ ] |  Privacy [ https://www.seattle.gov/privacy-statement?utm_medium=email&utm_source=govdelivery ]




________________________________________________________________________

This email was sent to mshinji3056@gmail.com using GovDelivery Communications Cloud on behalf of: City of Seattle, Washington · 707 17th St, Suite 4000 · Denver, CO 80202 GovDelivery logo [ https://subscriberhelp.granicus.com/?utm_medium=email&utm_source=govdelivery ]

body .abe-column-block { min-height: 5px; } table.gd_combo_table img {margin-left:10px; margin-right:10px;} table.gd_combo_table div.govd_image_display img, table.gd_combo_table td.gd_combo_image_cell img {margin-left:0px; margin-right:0px;} table.govd_hr {min-width: 100%;}
  • [登録者]City of Seattle
  • [言語]日本語
  • [エリア]Seattle, WA
  • 登録日 : 2024/11/08
  • 掲載日 : 2024/11/08
  • 変更日 : 2024/11/08
  • 総閲覧数 : 3 人
Web Access No.2308137