Notification

No Image

Construction Update: Denny Way Paving Project

Upcoming work on Denny Way including lane closures



City of Seattle Logo



*Construction Update: Denny Way Paving Project*

Upcoming work on Denny Way including lane closures
Construction Crews Working on the Denny Way Paving Project

*Construction is continuing on the Denny Way Paving Project*. The project will pave almost 12 blocks of Denny Way to improve mobility and enhance the overall travel experience for residents and commuters alike. Work includes asphalt paving, sidewalk improvements, bus stop changes, new pedestrian ramps, curb bulbs that shorten crossing distances, new stop bars painted on the road, and new "no turn on red" signs.

*Denny Way Paving Project*

Here’s what’s included in this email update:


* Anticipated Work in the Week Ahead
* Details on Upcoming Eastbound and Westbound Lane Closures
* What to Expect During Construction
* Project Team Contact Information

*Anticipated Work in the Week Ahead*

Crews are working on Denny Way between Taylor Ave and Dexter Ave and between 7th Ave and Dexter Ave, *with eastbound and westbound lane closures anticipated in the coming weeks**. *Our team is continuing to take out parts of the old sidewalk and parts of the road, check utility locations, update drainage, and then pour new sidewalk, new concrete road sections, and build new ramps for pedestrians. 

Map Detailing Work on Denny Way Between Taylor Ave and 6th Ave Including the Work Zone, Lane Closures and Sidewalk Work

*Taylor Ave and 6th Ave – Eastbound Lane Closures (4/5 to 4/7) - "Vine St Closure"*


* Work will start on Saturday at 6:30 AM with one eastbound lane closed from 6th Ave to Taylor and two eastbound lanes closed between Taylor and Vine Street. The eastbound traffic will be shifted to one of the westbound lanes. Closures will remain in effect until Monday morning at 5 AM when all lanes on Denny Way will be open to traffic during peak commute hours.
* Vine Street will be closed over the weekend. 
Map Detailing Work on Denny Way between 7th Ave and Dexter Ave Including Work Zone and Lane Closures

*7th Ave and Dexter Ave - Eastbound Lane Closures (4/4 to 4/7)*


* Work starts on Friday from 9 AM until 3 PM resulting in one eastbound lane closed for saw cutting.
* Work continues Saturday with one eastbound lane closed from 6:30 AM to 3 PM and two eastbound lanes closed from 3 PM on Saturday to 8 AM on Sunday for roadway demo, concrete and hydrant work. The eastbound traffic will be shifted to one of the westbound lanes.
* One eastbound lane will remain closed to allow concrete to be cured until 5 AM on Monday when we will open all lanes on Denny Way to general traffic for the Monday morning commute. 

*Taylor Ave and 6th Ave – Eastbound Lane Closures (4/7 to 4/11) - "Vine St Closure"*


* Work will continue on Monday with one eastbound lane on Denny Way closed from 9AM to 3PM Monday to Friday and reopened at 3PM each day to general traffic. 
* Vine Street will remain closed over the weekend. 

*7th Ave and Dexter Ave - Westbound Lane Closures (4/7 to 4/10)*


* One westbound lane will be closed from 9 AM to 3 PM from Monday to Thursday and reopened at 3PM each day to general traffic for sidewalk demo and install.

*7th Ave and Dexter Ave - Eastbound Lane Closures (4/11 to 4/14)*


* Work starts on Friday and continues throughout the weekend with one eastbound lane closed from 9 AM to 3PM for roadway demo and concrete work.
* Two eastbound lanes will be closed from 7AM on Saturday to 5AM on Monday and eastbound traffic will be shifted to one of the westbound lanes. 
* One lane will remain closed until 5 AM Monday. We will open all lanes to general traffic for the Monday morning commute. 

*What to Expect During Construction*

Work will happen during the daytime and asphalt paving will primarily occur at night, from 7 PM to 6 AM, Monday through Friday. There will be occasional weekend work. During construction, there will be lane closures along Denny Way, but one lane in each direction will remain open at all times. Sidewalk closures will occur, though pedestrian access will be maintained. Lane closures may last for 2-3 weeks at a time, and work zones will cover a few blocks at a time. Click this link [ https://links-1.govdelivery.com/CL0/https:%2F%2Flinks-1.govdelivery.com%2FCL0%2Fhttps:%252F%252Fwww.seattle.gov%252Fdocuments%252FDepartments%252FSDOT%252FMaintenanceProgram%252FDennyWay%252FPDF%252520%252520Map.pdf%253Futm_medium=email%2526utm_source=govdelivery%2F1%2F01000195de0e5237-75b9883b-fb9e-42f3-9012-bda2bdd30376-000000%2F-TUC3LM4VUfaaYlZaBMIc12GbTIZwUIYAzThTFiwPD8=398/1/01000195df262d13-f295f8c1-7020-4682-80bd-8354016b4693-000000/BANV7sp2PuKFbptfxtshWVmLYXKYAtLLA_GtzWeg59Y=398 ] to view a PDF of the project map.

Initial work will begin on Denny Way between Taylor Ave and Dexter Ave. Our team will take out parts of the old sidewalk and parts of the road, check utility locations, and then pour new sidewalk, new concrete road sections, and build new ramps for pedestrians.

*Things You Should Be Aware of During Construction* 

Construction will create some short-term changes to your area, including: 


* You may notice noise, dust, smell, and vibrations.
* You may need to change your walking route while we work on sidewalks, but we will provide signage for you to follow.
* Your business matters to us and we will provide advance notification of work and any impacts in person and provide you with a direct contact for questions. We will maintain access to your businesses at all times.
* You’ll notice asphalt paving work between 7 PM to 6 AM Monday-Friday with some daytime and possible weekend work when needed.
* Some of your parking and loading areas may shift near work zones but we are working at night to reduce these impacts.  
* If you are traveling along Denny Way, you may need to switch lanes around work areas. Signage will guide you on your journey.

*Questions or Want More Information?**  *


* Check out our project website [ https://links-1.govdelivery.com/CL0/https:%2F%2Flinks-1.govdelivery.com%2FCL0%2Fhttps:%252F%252Flinks-1.govdelivery.com%252FCL0%252Fhttps:%25252F%25252Fwww.seattle.gov%25252Ftransportation%25252Fprojects-and-programs%25252Fprograms%25252Fmaintenance-and-paving%25252Fcurrent-paving-projects%25252Fdenny-way-paving-project%25253Futm_medium=email%252526utm_source=govdelivery%252F1%252F01000195c9fa39fa-78f2910f-9a9e-4677-aada-f14955a77a00-000000%252FlLuC0owVsOnzx2dLnoMIwOcI-A-KBZ3_ULUE9ZlhQvM=397%2F1%2F01000195de0e5237-75b9883b-fb9e-42f3-9012-bda2bdd30376-000000%2F9ko9fQMB63LJY7HMQLvYtTGUXeLtCMbNOidiWEVOZJQ=398/1/01000195df262d13-f295f8c1-7020-4682-80bd-8354016b4693-000000/EzDkk-P7PrLfKR8lfDlLwDU3JBsTDwDwS6Hg9aE_TJY=398 ]
* Email the project team at DennyWay@seattle.gov <DennyWay@Seattle.gov>
* Call the project team at (206) 257-2243 (leave a voicemail and we will return your call)  
* Encourage your neighbors to sign-up for email updates [ https://links-1.govdelivery.com/CL0/https:%2F%2Flinks-1.govdelivery.com%2FCL0%2Fhttps:%252F%252Flinks-1.govdelivery.com%252FCL0%252Fhttps:%25252F%25252Fpublic.govdelivery.com%25252Faccounts%25252FWASEATTLE%25252Fsubscriber%25252Fnew%25253Fqsp=WASEATTLE_8%252F1%252F01000195c9fa39fa-78f2910f-9a9e-4677-aada-f14955a77a00-000000%252FfWj1bTesL7XJdNKu5fwxE-_dgwh56R2BwQDD990YWjw=397%2F1%2F01000195de0e5237-75b9883b-fb9e-42f3-9012-bda2bdd30376-000000%2FbNZCZwfYbYhxseThpaAvGXcGzoVBV7kOoBfGWaBU2iU=398/1/01000195df262d13-f295f8c1-7020-4682-80bd-8354016b4693-000000/LsTkZesmpXDzdAPZdTJlutUciSIUZ_oEmb4GozsNOI0=398 ] to stay informed on the project as construction continues  

Thank you for your support during construction, and please don’t hesitate to reach out with any questions or comments.  

Sincerely, 

Darrell Bulmer

Denny Way Paving Project Communications and Outreach Lead

Seattle Department of Transportation

"Để biết thông ,n bằng ngôn ngữ của quý vị về việc chúng tôi thay thế bề mặt đường và thực hiện các cải ,ến khác trên đường Denny Way, vui lòng gọi (206) 257-2243. Vui lòng cho chúng tôi biết bằng ,ếng Anh ngôn ngữ mà quý vị muốn sử dụng. Chúng tôi cung cấp miễn phí dịch vụ phiên dịch và thông dịch."" "

有關我們在 "Denny Way"" "上重鋪路面和進行其他安全改進工程的資訊(以您的語言),請致電 "(206) 257-2243"。請用英語 告訴我們您想要的語言。我們免費提供筆譯和口譯服務。

"Si desea información en su idioma acerca de nuestro trabajo de reemplazo de la superficie de la carretera y otras mejoras en Denny Way, llame al (206) 257-2243. Díganos en inglés cuál es su idioma preferido. Ofrecemos servicios de traducción e interpretación gratuitos."

Learn More [ https://www.seattle.gov/transportation/projects-and-programs/programs/maintenance-and-paving/current-paving-projects/denny-way-paving-project?utm_medium=email&utm_source=govdelivery ]





*Seattle City Hall*

600 4th Avenue

Seattle, WA 98104

*Phone: 206-684-2489 (CITY)*

facebook [ https://www.facebook.com/cityofseattlegov/?utm_medium=email&utm_source=govdelivery ]twitter [ https://twitter.com/cityofseattle?utm_medium=email&utm_source=govdelivery ]instagram [ https://www.instagram.com/cityofseattlegov/?utm_medium=email&utm_source=govdelivery ] [ https://twitter.com/cityofseattle?utm_medium=email&utm_source=govdelivery ] seattle dot gov

Manage Preferences [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/edit?preferences=true#tab1 ]  |  Unsubscribe [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/one_click_unsubscribe?verification=5.7e4abd93610d77ba0dce3e5196581a5c&destination=mshinji3056%40gmail.com ]  |  Contact Us [ http://www.seattle.gov/customerservice/contact.htm?utm_medium=email&utm_source=govdelivery ]  |  Help [ https://subscriberhelp.govdelivery.com/ ] |  Privacy [ https://www.seattle.gov/privacy-statement?utm_medium=email&utm_source=govdelivery ]




________________________________________________________________________

This email was sent to mshinji3056@gmail.com using GovDelivery Communications Cloud on behalf of: City of Seattle, Washington · 600 Fourth Avenue · Seattle, WA 98104 GovDelivery logo [ https://subscriberhelp.granicus.com/?utm_medium=email&utm_source=govdelivery ]

body .abe-column-block { min-height: 5px; } table.gd_combo_table img {margin-left:10px; margin-right:10px;} table.gd_combo_table div.govd_image_display img, table.gd_combo_table td.gd_combo_image_cell img {margin-left:0px; margin-right:0px;} table.govd_hr {min-width: 100%;}
  • [สมาชิกที่ลงทะเบียน]City of Seattle
  • [ภาษา]日本語
  • [แอเรีย]Seattle, WA
  • วันที่ลงทะเบียน : 2025/04/04
  • วันที่โพสต์ : 2025/04/04
  • วันเปลี่ยนแปลง : 2025/04/04
  • จำนวนรวมของการเปิดดู : 23  คน
เบอร์ Web Access 2673255