Construction update for May 23 - June 6
Seattle Department of Transportation logo
Georgetown to Downtown Safety Project Update
Crews have been making steady progress on completing the protected bike lanes on Airport Way S. We rechannelized the road to accommodate the future protected bike lane and other design elements that aim to improve safety for all travelers. *The new bike lanes remain closed through the entire project route until the project is complete.* *Please follow bike lane closure and detour signage to follow the pedestrian paths through these intersections.* These closures are necessary to keep cyclists safe through intersections while safety elements are being installed.
Over the next few weeks, you’ll see the following construction activities in the area:
* Completing final inspections of various project elements along the project corridor.
* Installing new signage and pavement markings along the project corridor, beginning at 6th Ave S and S Forest St and working south.
* Electrical and signal improvements at Airport Way S and S Lucile St and at 6th Ave S and S Spokane St
*What to expect during construction: *
* *Truck detour to S Lucile St is no longer in effect. *Right and left turns for freight vehicles from Airport Way S to S Lucile St have now been restored.
* Northbound lane reduction along Airport Way S is no longer in effect. The permanent lane configuration has been installed. Drivers will notice a single dedicated left turn lane onto westbound Lucile St. and a single through lane northbound on Airport Way. Additional pavement markings and signs have been added for advance notice of lane assignments.
* Pedestrian access will be maintained. *Pedestrian detours may be longer than usual*
* Access to businesses will be maintained
* Typical work hours are from Monday to Friday, starting at 9:00 AM and finishing at 3:00 PM
* We will avoid work and traffic control during the peak hours of 7:00 AM to 9:00 AM and 4:00 PM to 6:00 PM
* We may need to temporarily change the traffic flow to accommodate the construction work.
* There will be temporary restrictions on parking.
* Some of the work activities might be noisy. This includes using backup alarms for safety, heavy vehicles, and power tools.
* Some construction may require temporary changes to bus routes. Visit the King County Metro website [ https://kingcounty.gov/en/dept/metro/rider-tools/service-advisories?utm_medium=email&utm_source=govdelivery ] for rider alerts.
We will continue to post bi-weekly construction updates on this webpage and the project listserv through construction.
*Construction progress*
Airport and Lucile new curb landscaipng
Looking at the newly constructed pedestrian curb at S Lucile St from Airport Way S, ready for landscaping to be installed
Workers put the finishing touches on the newly paved truck apron on Airport Way S and S Lucile St
Workers put the finishing touches on the newly paved truck apron on Airport Way S and S Lucile St
________________________________________________________________________
Project Design
During construction, you will see us making the following changes:
* *Two-way protected bike lane *on the west side of the street from Airport Way S and S Lucille St to S Nevada St and 6th Ave S
* *One-way protected bike lanes *on 6th Ave S from S Nevada St to S Forest St
* *Two-way, center turn lane *on 6th Ave S from south of S Forest St to S Spokane St, making it safer and easier for vehicles to enter and exit driveways
* *S Spokane St and Airport Way S*: New traffic signal, signalized bike crossing, and bike ramp
* *S Lucile St and Airport Way S*: New signalized bike crossing, ADA curb ramps, and refreshed crosswalk markings
* *All-way stop *on 6th Ave S at both the intersections with S Alaska St and S Nevada St
* *Raised bus stop *on the west side of Airport Way S at S Edmonds St
* *Parking removal *on the west side of 6th from Alaska to Industrial to allow for two-way freight movements.
Project corridor map
Map of improvements to be constructed on 6th Ave S, S Alaska St, and Airport Way S.
Learn more about the project [ https://www.seattle.gov/transportation/projects-and-programs/programs/bike-program/protected-bike-lanes/georgetown-to-downtown-protected-bike-lane?utm_medium=email&utm_source=govdelivery ]
________________________________________________________________________
How to stay informed
* Call our project hotline at (206) 900-8750 [ tel:%20+1%20(206)%20900-8750 ]
* Email us at GeorgetownToDowntownSafety@seattle.gov
* Visit our project webpage [ https://www.seattle.gov/transportation/projects-and-programs/programs/bike-program/protected-bike-lanes/georgetown-to-downtown-protected-bike-lane?utm_medium=email&utm_source=govdelivery ] to:
* Read about project progress
* Sign up for email updates
Thank you,
Ching Chan
Public Engagement Lead
Levy to Move Seattle Logo
*Seattle Department of Transportation*
700 5th Avenue
Suite 3800
Seattle, WA 98104
*Phone: 206-684-7623*
facebook [ https://www.facebook.com/SeattleDOT/?utm_medium=email&utm_source=govdelivery ]front porch [ https://sdotblog.seattle.gov/?utm_medium=email&utm_source=govdelivery ]r s s feed [ https://sdotblog.seattle.gov/feed/?utm_medium=email&utm_source=govdelivery ]twitter [ https://twitter.com/seattledot?utm_medium=email&utm_source=govdelivery ]flickr [ https://www.flickr.com/photos/sdot_photos?utm_medium=email&utm_source=govdelivery ]instagram [ https://www.instagram.com/seattledot/?utm_medium=email&utm_source=govdelivery ]youtube [ https://www.youtube.com/seattledot?utm_medium=email&utm_source=govdelivery ]linkedin [ https://www.linkedin.com/company/seattle-department-of-transportation?utm_medium=email&utm_source=govdelivery ] seattle dot gov
Manage Preferences [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/edit?preferences=true#tab1 ] | Unsubscribe [ https://public.govdelivery.com/accounts/WASEATTLE/subscriber/one_click_unsubscribe?verification=5.7e4abd93610d77ba0dce3e5196581a5c&destination=mshinji3056%40gmail.com ] | Contact Us [ https://www.seattle.gov/transportation/about-sdot/contact-us?utm_medium=email&utm_source=govdelivery ] | Help [ https://subscriberhelp.govdelivery.com/ ] | Privacy [ https://www.seattle.gov/privacy-statement?utm_medium=email&utm_source=govdelivery ]
________________________________________________________________________
This email was sent to mshinji3056@gmail.com using GovDelivery Communications Cloud on behalf of: City of Seattle, Washington · 600 Fourth Avenue · Seattle, WA 98104 GovDelivery logo [ https://subscriberhelp.granicus.com/?utm_medium=email&utm_source=govdelivery ]
body .abe-column-block { min-height: 5px; } table.gd_combo_table img {margin-left:10px; margin-right:10px;} table.gd_combo_table div.govd_image_display img, table.gd_combo_table td.gd_combo_image_cell img {margin-left:0px; margin-right:0px;} table.govd_hr {min-width: 100%;}
印刷された情報をサイトで見るには、上記URLまたはQRコードからアクセスできます。